  1. In the middle of the picture is the ramp leadin gdown to the parking garage and next to it is the oading dock for the building. Due to weather delays it took longer to pour the rest of the loading dock because we didnn't want the rain to damage the finish. The forms are being installed for the elevator shaft walls and will be used as the form for the deck pour also. Near the end of the photo set you can see blck lines criss crossing the deck, these are the pt cables that strengthen the deck. After the concrete has been poured and cured for a couple of days these cables will be stretched and pull up the deck. The way they ae designed and installed affects the weight load for the floor, once we get to the uper floors the floor will only be 7.5 in thick!