Thursday, March 3, 2011

Construction Photos February 2011 (Phase I)




























1 comment:

  1. We still have a section of basement slab left to pou, usually there are a lot more pipes and other thihgs in the basement slab but since we are underwater at this point there is not much that will be included in this pour. In the are that has been poured we are starting to set u scaffolding for the entry ramp into the parking garage. The way the ramp connects into the other areas of the 1st floor slab requires that it be poured first. We are waiting for good weather to pour this so the finish will be really nice, since it is a small pour we can contionue to form up the rest of the deck around the ramp and it will not cause any delays to the schedule.