Wednesday, September 7, 2011

Construction Photos Phase 1 - August 2011












































1 comment:

  1. Even though the building isn't getting taller anymore there is still a lot of work going on inside. Floors 1-4 are available for hanging air duct and electrical conduit. Elevator shaft steel is being welded in place and once the roof is finished the elevator can be started. There are 2 pictures where there is an orange boom extending in the middle of the picture. This is the concrete pump truck sending concrete to the roof. The roof pour was divided into 2 sections.

    ReplyDelete