Construction Photos Phase II-October 2012
























1 comment:

  1. You can see the entire process of the 2nd floor North deck. The begining part is getting the scaffolding up from the 1st floor. It is wheeled out into the street where the crane picks it up and distributes it to the different areas of the new deck. While this is happening the elevator shaft is formed and poured which is locaed in the middle of the screen. Once all of the decking is in place the rebar is set intop place and followed by electrical conduit. After the pour it takes 3 days for the concrete to cure enough for the scaffolding to be removed and sent up to the next floor and the process is repeated all over again.