Construction Photos Phase II - May 2013



































1 comment:

  1. Although the building isn't getting any higher there is still a lot of work going on. The most obvious is that windows are in on the 4th floor and have also started on the 5th floor. Brick has also started but it is very difficult to see in the pictures, there will be a lot more installed next month. There are some areas on the building that are neon blue, this is waterproofing applied before the brick is installed, all of the areas that are neon blue will be covered with brick next month. The elevators are in full swing and we should have some running in about 5 weeks. Framing is also complete on all floors and sheet rock will follow soon.