Construction Photos Phase II - April 2013














 





















1 comment:

  1. We have poured the last section of the roof and that will open up the entire building for the other trades to begin working, up until this point there was scaffolding on most of the floors to support the weight of the wet concrete during the pours but now that this is complete the installation pace will pick up speed. Most noticeably the first panels of windows have started to go in, there are 2 window crews onsite, the first is doing all of the prep work in front of the second crew who is concentrating just on window panel installation. They are getting at least 20 panels installed each day.